Back to course

Work, Pipes and Rates

15 minbeginnerModule 2: Quantitative ReasoningContinues from hat-rates-speed-distance
15 min · Module 2: Quantitative Reasoning · Rates

Why This Matters

Work questions are the quantitative section's most procedural family. "A can do a job in 12 days and B in 18" is not a problem to be intuited; it is a template to be applied, and the template never changes. Learn four setups — worker-days, combined rates, pipes, and partway joins — and you can convert a whole block of questions into mechanical arithmetic.

The classic failure here is adding times. Two workers taking 12 and 18 days do not take 30 days together, and they do not take 15. The reason is worth understanding once, because it is the same reason average speed is not the average of speeds.

A Simple Model

Convert every worker into a rate: the fraction of the job they finish in one unit of time.

worker who takes a days alone has rate 1 ÷ a jobs per day

When workers act together, their rates add, because in one day they collectively finish the sum of their daily shares.

1 ÷ T = 1 ÷ a + 1 ÷ b   so   T = ab ÷ (a + b)

For two workers the shortcut T = ab ÷ (a + b) is worth memorising: 12 and 18 days give (12 × 18) ÷ 30 = 7.2 days, and the answer is always less than the smaller of the two times — a one-second sanity check that kills most wrong options.

The Actual Detail

Setup 1 — Worker-days

If the work is measured in people rather than days, the total work is constant:

workers × days = constant   (more workers means fewer days)

Fifteen workers finish a job in 20 days, so the job is 300 worker-days; 25 workers need 300 ÷ 25 = 12 days. If the question mentions hours per day, convert to worker-hours first: 15 workers × 20 days × 8 hours = 2,400 worker-hours.

Setup 2 — Combined rates

Add the fractions, then invert. Three workers follow the same rule: 1 ÷ T = 1 ÷ a + 1 ÷ b + 1 ÷ c, so 6, 12 and 12 days give 1/6 + 1/12 + 1/12 = 1/3, which is 3 days.

Setup 3 — Pipes filling and draining

An inlet adds its rate; an outlet subtracts. A pipe filling in 6 hours and a drain emptying in 9 hours have a net rate of 1/6 − 1/9 = 1/18, so the tank fills in 18 hours — slower than the inlet alone, which is the point of the question.

Setup 4 — Joining, leaving, alternating

The answer is always below the fastest time. Two or more workers together must beat the best individual time, and combined with a drain the result must be worse than the inlet alone. Checking against those two bounds takes two seconds and eliminates three of four options on most questions in this family.
Never add times, and never add efficiencies as times. The two errors are mirror images: 12 and 18 days is not 30 and not 15, and a worker who is 50% more efficient than a 10-day worker takes 10 × 2/3 = 6.67 days, not 5 days.

Worked Examples

1. A finishes a job in 12 days, B in 18. Working together, how long?

1/12 + 1/18 = 3/36 + 2/36 = 5/36, so T = 36/5 = 7.2 days. The shortcut agrees: 216 ÷ 30 = 7.2. Sanity check: less than 12, as it must be.

2. A works alone for 4 days, then B joins. A alone would need 10 days; B alone would need 15. When is the job finished?

A's four days produce 4/10 = 0.4 of the job, leaving 0.6. Working together the rate is 1/10 + 1/15 = 1/6, so the remaining work takes 0.6 × 6 = 3.6 days. Total: 4 + 3.6 = 7.6 days.

3. Twelve workers build a wall in 15 days. How long would nine workers take?

Total work = 12 × 15 = 180 worker-days, so nine workers need 180 ÷ 9 = 20 days. Fewer workers, more days — inverse proportion.

4. A is twice as fast as B, and together they finish in 8 days. How long would A take alone?

Let B's rate be r, so A's is 2r and the total is 3r = 1/8, giving r = 1/24. B alone would need 24 days and A alone 12 days. Check: 1/12 + 1/24 = 3/24 = 1/8.

Try It

A can paint a room in 6 days and B in 12. Together?

Fifteen workers complete a job in 20 days. How many days for 25 workers at the same rate?

An inlet fills a tank in 4 hours and a drain empties it in 6 hours. With both open, how long to fill it?

A does a job in 10 days and B in 15. They work together for 3 days. What fraction of the job remains?

Check Your Understanding

Without looking back: how do you turn "a days alone" into a rate, and what happens to rates when workers act together?

The answer: the rate is 1 ÷ a jobs per day, and rates add when workers act together.

A worker who needs a days alone has a rate of 1 divided by jobs per day. When workers act together their rates . For two workers taking 12 and 18 days, the combined time is days, and the total work in a worker-days problem is workers days.

Apply It

A question reads: "Pipe A fills a tank in 8 hours. Pipe B fills it in 12 hours, and a drain C empties it in 24 hours. All three are opened. How long until the tank is full?" Solve it and give the sanity check.

Show the reasoning

Net rate = 1/8 + 1/12 − 1/24. Over a common denominator of 24: 3/24 + 2/24 − 1/24 = 4/24 = 1/6. So the tank fills in 6 hours.

The sanity check is a bound test: without the drain, pipes A and B together fill the tank in 4.8 hours (1/8 + 1/12 = 5/24), so the answer must be greater than 4.8 and less than 8 (the best single pipe). Six hours satisfies both bounds, which eliminates any option outside that window without a single extra calculation.

Connect

Rates are done. The next lessons turn to counting and probability — how many ways something can happen, and how likely a given outcome is — which is the last block of quantitative material with its own vocabulary.